Overview
- Key
- data_centre_commissioning_date
- Default unit
- -
- Data type
- date
- Matching type
- deterministic
- Regulation
- EnEfG
- Generalisability
- Likely general Ein Inbetriebnahmedatum trennt in vielen Anlagen- und Produktvorschriften Bestand von Neubau; das Merkmal ist deshalb als Datumsmerkmal angelegt.
- Description
- Date on which the data centre started or will start operation, as an ISO date. The Act ties different requirements to the 1 July 2026, 1 July 2027 and 1 July 2028 cut-offs.
Operators
No operators.
| Regulation | Rule set | Condition |
|---|---|---|
| EnEfG | Data centres that started operation before 1 July 2026 | Date on which the data centre started operation < 2026-07-01 |
| EnEfG | Data centres that start operation from 1 July 2026 | Date on which the data centre started operation >= 2026-07-01 |